Monash Village — Monash University Caulfield Campus

Western Precinct Development

The $300 million Equiset development Monash Village, will provide retail, student apartments, education, and office precincts over three basement levels and six buildings, linking a
diverse range of communities and creating plazas that will be the heart of campus and
community village life.


Equiset will undertake a significant redevelopment of the existing retail and University facilities located in the Caulfield Major Activity Centre, at the western end of the University campus.

A key aim of the project (Monash Village) is to integrate the University campus with the community and create an active, vital and sustainable town centre.

Monash Village is a project that has taken seven years of design consultation and exemplifies Equiset’s capacity to provide complex property solutions that deliver a
true benefit to all stakeholders. Equiset’s role is that of owner, developer, project manager and builder.

Features

  • Major urban renewal
  • Integrating the campus with the community
  • Ecologically sustainable design
  • Sustainable transport initiatives
  • New town centre
  • Neighbourhood shopping centre with full line Coles supermarket
  • Attractive public open spaces with connections to Derby Road and public transport

Statistics

  • Land area 10,000m2
  • 3,900m2 Coles supermarket
  • 3,200m2 specialty retail with 39 shops
  • 436 student apartments providing 612 beds in three separate buildings
  • 12,000m2 education space in one building
  • 5,500m2 office space in two buildings
  • 578 car spaces
  • Project value $300 million

Project program/milestones

  • Tender Submission
  • 24 September 2004
  • Development Agreement and
    Contracts of Sale
  • 5 July 2006
  • Minister for Planning approval
    of Amendment C53
  • 18 October 2006
  • Council Planning Permits
  • 14 November 2007
  • Council Planning Permit for
    Lot 5 Education East (Law Building)
    June 2008*
  • Amended Planning Permits
    for Lot 1 and Lot 6
    August 2008*
  • Effective Date (Conditions
    Precedent satisfied) end
    November 2008*
  • Pre-selling and pre-leasing period
  • July 2008 to March 2009*
  • Early Works (Services Infrastructure) November 2008 to March 2009*
  • Financial Close March 2009*
  • Close Caulfield Plaza
    March 2009*
  • Main Works
    March 2009 to December 2011*
  • Coles Supermarket and Food Market open June 2011*
  • Student apartments complete
    December 2011*
  • Education (Law Faculty Building) complete December 2011*
  • Office buildings complete
    June 2012*
    * Target