Equiset will undertake a significant redevelopment of the existing retail and University facilities located in the Caulfield Major Activity Centre, at the western end of the University campus.
A key aim of the project (Monash Village) is to integrate the University campus with the community and create an active, vital and sustainable town centre.
Monash Village is a project that has taken seven years of design consultation and exemplifies Equiset’s capacity to provide complex property solutions that deliver a
true benefit to all stakeholders. Equiset’s role is that of owner, developer, project manager and builder. |
 |
Features
- Major urban renewal
- Integrating the campus with the community
- Ecologically sustainable design
- Sustainable transport initiatives
- New town centre
- Neighbourhood shopping centre with full line Coles supermarket
- Attractive public open spaces with connections to Derby Road and public transport
Statistics
- Land area 10,000m2
- 3,900m2 Coles supermarket
- 3,200m2 specialty retail with 39 shops
- 436 student apartments providing 612 beds in three separate buildings
- 12,000m2 education space in one building
- 5,500m2 office space in two buildings
- 578 car spaces
- Project value $300 million
Project program/milestones
- Tender Submission
24 September 2004
- Development Agreement and
Contracts of Sale
5 July 2006
- Minister for Planning approval
of Amendment C53
18 October 2006
- Council Planning Permits
14 November 2007
- Council Planning Permit for
Lot 5 Education East (Law Building)
June 2008*
- Amended Planning Permits
for Lot 1 and Lot 6
August 2008*
- Effective Date
(Conditions
Precedent satisfied) end
November 2008*
- Pre-selling and pre-leasing period
July 2008 to March 2009*
- Early Works (Services Infrastructure) November 2008 to March 2009*
- Financial Close March 2009*
- Close Caulfield Plaza
March 2009*
- Main Works
March 2009 to December 2011*
- Coles Supermarket and Food Market open June 2011*
- Student apartments complete
December 2011*
- Education (Law Faculty Building) complete December 2011*
- Office buildings complete
June 2012* * Target
|
 |
|